Monday, June 19, 2017

Parks Accomplishments and Goals



The Park and Recreation Committee have been very excited about their most recent projects.  The Fishing Boardwalk was not working out as intended and needed a new plan to achieve the goals for the structure.  Fishing that required a fish to be dragged over slim to no water didn’t make sense.  The boardwalk was removed and reconstructed with floats and new railing structures.  The channel at the location was excavated so the boardwalk was able to float.  It was reconstructed in pieces, floated in place and linked together.  After assembly a review of the finished project revealed that the additional railing on each end caused those sections to dip somewhat.   This prompted the addition of an additional float leveling the structure.  The project has a nice feel, looks good, and provides much better fishing than the previous setup. 

Another project that has been ongoing is that of the Disc Golf Course.  We currently have 9 holes established and it was hoped that the back nine would be completed last summer.  With the numerous bad storms that hit Breezy Point last summer the Public Works crew were busy with more pressing matters.  Some of the course was cleared for fairways and brush piles were made.  A portion of the work continued to occur during the winter months with some tree clearing and brush being burned, but a good portion of the work needed to happen during warmer months. 

After seeing the course being used some improvements were felt necessary.  The tee mats were not staying in place.  With rains, sand was washing over them as well.  A better solution was required.   The tee marking which were painted on the mats was wearing off.  A better solution was needed for these.  Park Benches were installed in the front nine but were needed for the back nine.  Signage and the expansion of the parking area with improved drainage were also needed. 

The Parks Committee discussed these needs and agreed to amend the Capital Improvement Plan (CIP) to provide for these additional costs.  Tee boxes will be installed, tee makers of etched stones will be installed, park benches and signage will be purchased and the parking area will be expanded and regraded.  The plan was approved by the City Council at the June meeting.  These improvements are planned to be completed this summer. 

The CIP was also amended to deal with the possible paving of a parking lane at the Fishing Boardwalk.  For 2019 the committee felt we needed to have the city park reviewed towards a master development plan.  They have lots of ideas about what could go in the park but wanted to thoroughly review what should be included and what should go where.  Finishing out the plan it is hoped another ball field can be included in the park.  They feel the space available maybe too small for a regulation field so have contemplated a little league field. 

The plan has a number of long range goals.  Additional improvements to the ball filed are included.  Trails along all the collector streets are proposed.  There is mention of an additional disc golf course and a mountain bike trail near the existing disc golf course.  Other amenities being considered include a bocce ball court and a pickle ball/tennis court.  Lots of great ideas are being considered and are part of the long range plans.  With time and money they hope to make parks a more viable part of Breezy Point.     




Tuesday, June 6, 2017

2016 Audit Summary



The city is required to conduct an annual audit conducted by an independent auditor.  The firm of Schlenner Wenner & Co. was hired to conduct our audit.  The audit was presented to the city council at their April meeting. 

Some of the highlights from the presentation include: 

·         Revenues were up slightly from that of 2015 with an increase of $13,778
Building permit revenues were very strong with $56,616 over budget
Fund transfers of $69,000 as budgeted were not transferred

·         Expenditures were over budget for 2016 by $46,068
General Government category of expenses was $326,376 under budget
Capital Outlay expenses were higher than anticipated by $207,184
Operating Transfers to Revolving Capital Fund was more than budget by $210,491

·         Debt Service Funds ended the year with $11,550 revenues over expenses
·         One General Obligation Bond is outstanding with a balance of $1,695,000
·         Revolving Capital Fund ended the year $272,229 stronger than 2015
·         Cemetery Fund balance is $106,704, which includes the Perpetual Care Fund
·         EDA Fund balance is $5,120
·         Sewer Fund balance is $3,347,530 which includes Capital and Operating Funds

This budget year was somewhat unusual.  A grant replaced some of the capital expenditures incurred with the project not being budgeted.  Building permits were far stronger than anticipated which affects both revenues and expenditures, both beyond budget.  Revenues that are earmarked for capital expenditures were stronger than anticipated increasing the transfer to the Revolving Capital Fund.   The city is doing very well financially and is positioned well for the future.


Thursday, May 18, 2017

Building up the Capital Improvement Sewer Fund



The city conducts an annual audit which puts the city’s finances in perspective as to what was spent, what was collected, and what are the balances in the various accounts of the city.  After the audit these balances are compared to a threshold that was established in the city’s Comprehensive Fund Balance Policy.  The policy in general provides for a minimum amount of cash to be held as undesignated reserves to be used for cash flow and/or unbudgeted expenses.

The threshold for the General Fund is 40% to 45% of the following years budgeted expenses.  The threshold for the sewer fund has been maintained at 45% but there is no formal threshold for sewer funds.  Sewer funds are split into either operating or capital improvement accounts.  Sewer funds in excess of the amounts are transferred to long term resource accounts.  If funds were to dip under the threshold a decision would need to be made as to how those funds would be replenished. 

In reviewing these balances from year end the General Fund fell within the 40-45% threshold so no transfer was recommended.  The Sewer Fund on the other hand had resources in excess of 45% in the operating fund.  The amount that exceeded the threshold was $23,469.  These funds were recommended to be placed in the Sewer Capital Improvement Fund.  As such the council approved the transfer and funds will be moved.   

Monday, May 8, 2017

Gravel Packer



Most people are familiar with a grader going down the road to smooth out the gravel.  In the spring the grader brings gravel from the shoulder area that was displaced from winter plowing and smooths it out over the road.  This effort of grading continues to be accomplished periodically throughout the summer months as needed.  

As roads are graded the material is repositioned on the roadway in a relatively loose manner.  We have relied on traffic to compact this material. If it rains before it gets compacted it becomes a muddy mess.  If it dries out too much without compaction it creates dust.  The dust eliminates some of the fine materials leaving the material as mostly stones.  A good gravel roadway needs gravel and some clay materials to hold it together to create a smooth surface.

The city continues to look to ways to improve and manage gravel roadways.  One approach not previously used in the past was that of using a gravel packer.  A packer is a multi-tired unit that applies pressure across the width of the roadway that was just graded. Packing the roadway just after it has been graded firms up the surface allowing for a smoother roadway that is expected to hold up longer.  It is also hoped this will reduce grading time in general as it shouldn’t be needed as often. 

Another advantage of the packer is using it when gravel is added to improve its base.  With an inch or two of new gravel being spread the hope has been that traffic would firm it up.  This doesn’t work as well as you might think.  Compaction becomes uneven and it can even create ruts.  Placing gravel with the packer improves the operation and the final outcome.  A better finished project is the result. 

The city council considered the purchase of a packer unit at its May meeting.  Under the state bid the unit was purchased for $33,920.00.  The budget for this piece of equipment was $35,000.  The city will be using this unit as soon as it arrives so hopefully we’re on the road to better gravel roadway surfaces.  

Thursday, May 4, 2017

Roadway Vacation



The majority of streets and right-of-ways that become our transportation system came about through the platting of a subdivision.  When lots are created public right-of-ways are required to get people to and from the lots.  With a platting of a public right-of-way the plat dedicates to the public the use of the property in perpetuity.  To remove a platted right-of-way the statutes require a procedure known as a vacation of them.  The process involves a public hearing with published and mailed notice to affected property owners.  The process can be initialed by a petition of the abutting property owners or by action of the city council.

A petition was received and a public hearing was held on May 1st to consider the vacation of a small strip of right-of-way that lead from the platted portion of Hilltop Drive to the shore of Lake Ossawinnamakee.  This right-of-way is 16.5 feet wide and approximately 210 feet long.  Given it terminates at a lake, providing public access, the  Commissioner of the DNR is also given notice.  They are invited to comment on the proposed vacation.  At the public hearing individuals were given the opportunity to speak for or against the proposed vacation.  A good amount of testimony was heard.  The statutes require the city council find it is in the best interests of the city to vacate a roadway.  In other words the city must find a benefit in the vacation.

The DNR, in responding to the proposed vacation had recommended denying it based on a number of factors. 
1.    The right of way was dedicated to the public for public use.  It provides multimodal access to the lake.
2.    The vacation as proposed provides no public benefit to match the value of the current and potential public resource.
3.    Although the access is generally undeveloped and the DNR does not advocate improvements, it provides lake access.  They cannot anticipate what needs may exist for public access on this lake in 100 years, but once this valuable land leaves public ownership; it is likely gone for good.
4.    The proposed road vacation negatively impacts access to public waters.  The public has the right to use all of the public waters in the state.  The public includes persons other than those in the immediate vicinity.

This access point also provides a location in which the Fire Department can access the lake to draft water in an emergency, as there are no fire hydrants to use.  It was stated that this is part of their fire protection program.

At the conclusion of the public hearing the council considered the request and voted unanimously to deny the request stating the above findings as well as the need to preserve the option for fire protection.