Tuesday, April 19, 2016

2017 Road Improvements?



Accomplishing road improvements takes some time.  There is a process that needs to be followed with public improvements.  These include the formal bidding requirements that need to be followed.  These processes are prescribed by Minnesota Law.  We’re already working on road improvements for 2017.

One step at a time! The process starts with some planning.  What projects make sense and how are we going to address the financing?  

The Road Committee recommended several streets in Breezy Point to be paved.  These streets are those in the subdivision of Whitebirch 6th Addition and include: Navaho Trail, Pima Circle, Zuni Circle, Aztec Circle and Pawnee Circle.  The recommendation was received and accepted by the city council. 
 
Street improvements are paid for by assessments levied on benefiting properties.  Financing of the improvements is being accomplished with existing revenues.  By using resources without bonding a good deal of costs are eliminated.

In following the process prescribed by law to assess improvements the first action needed is for the city council to request a feasibility study.  This study defines what is needed to be done to install the road improvements.  Typically the roadway surface is viewed for adequacy of base and drainage.  Ditches may need to be upgraded along with culverts, outlets or other requirements.  This study has been requested by the city council.  

Accomplishing this study requires a contract with the engineer to do the study.  This was approved as well in moving the process forward.  Once the study is accomplished the city council is informed of the outcome and considers the possibility of the road improvement project.  If it seems feasible and reasonable to accomplish the improvements they will call for a public hearing.  All affected property owners are given notice of the hearing and the preliminary costs are reviewed along with related assessment amounts.  

With a favorable outcome from the improvement hearing the council would take action on the remaining steps of ordering plans and specifications, seeking bids and holding a final assessment hearing prior to ordering the project.  If the outcome at the assessment hearing seems to indicate the owners want the improvements, the council orders them and awards the contract for construction.  

Considering the time lines; the feasibility study will be completed in a month or two.  The improvement hearing will be held a couple of weeks after that.  If the process moves forward plans and specifications are developed for approval in late fall, early winter.  Bids are then received in February or March. The assessment hearing follows within about three weeks.  Subject to that outcome, the ordering of the project and award of the contract can take up to an additional six weeks.  Construction would occur sometime after road restrictions are lifted in the spring.  Project completion occurs in the summer of 2017 with final restoration in the fall.  

It takes a process, and time, to get road improvements accomplished.