Wednesday, February 19, 2014

Progress on Creek Circle and Whitebirch Drive



The City Council has continued the progress on the extension of sanitary sewer and paving for Creek Circle and portions of Whitebirch Drive.  Plans and specifications were reviewed and approved which clears the way for seeking of bids on the project.  Bids will be received on February 28th for the project.  With early bids it is hoped the city will see a number of bidders and competitive pricing. 

The project will serve 15 residential lots along Creek Circle and 18 townhouse units in a development known as Whitebirch Village. 

Once bids have been received the city can call for an assessment hearing as costs will be known.  A special meeting has been proposed to address assessments the week of March 31st.  If the project is to be constructed, construction would start around the first of June.  Construction is proposed to be completed in the fall.